Highland Copper Announces Positive Feasibility Study Results for its Copperwood Project in Michigan - IRR of 18% After Tax, Capital Cost of $275 M and an Average Payable Copper Production of 61.7 M Lbs per Year


LONGUEUIL, Quebec, June 15, 2018 (GLOBE NEWSWIRE) -- Highland Copper Company Inc. (TSXV:HI) (OTCQB:HDRSF) (“Highland” or the “Company”) is pleased to announce the results of a feasibility study (the “Feasibility Study”) for its 100%-owned Copperwood project located in Gogebic County, in the Western Upper Peninsula of Michigan, U.S.A. (the “Copperwood Project”).

Highlights of the Copperwood Project Feasibility Study

(All amounts in this news release are in US dollars, unless otherwise indicated. Due to rounding, numbers presented throughout this release may not add up precisely to the totals provided.)

  • After-tax internal rate of return (“IRR”) of 18%
  • Initial capital expenditures of $245 million, net of pre-production revenue of $30 million
  • Life-of-mine (“LOM”) cash costs of $1.53/lb, including royalties and $1.29/lb in the first five years of production
  • Proven and Probable Reserves of 25.4 M tonnes @ 1.43% Cu and 3.83 g/t Ag, containing 801.8 M lbs of copper and 3.1 M oz of silver
  • Additional Mineral Resources of 49.9 M tonnes @ 1.15 % Cu and 3.42 g/t Ag in the Inferred category, containing 1.3 B lbs of copper and 5.5 M oz of silver using a 1% Cu cut-off
  • Average annual LOM payable copper production of 61.7 M lbs and 100,570 oz of silver
  • Initial copper production expected in early 2021

“A major step forward for the Copperwood Project” said Denis Miville-Deschênes, President and CEO of Highland Copper. “The Feasibility Study demonstrates the significant potential of this project located in a great historic mining jurisdiction. Based on the results of the study, we can now focus on putting in place a comprehensive financing package.” He added “The development of a mine at Copperwood represents a tremendous opportunity to create hundreds of jobs in the region.” 

The Feasibility Study was conducted by, and under the supervision of, G Mining Services Inc. (“GMSI”) in collaboration with SGS Canada Inc. (Lakefield), Lycopodium Minerals Canada Ltd, Golder Associates and Foth Infrastructure and Environment. The study provides a comprehensive overview of the Copperwood Project and defines an economically feasible, technically and environmentally sound project.

Opportunities to Increase Copperwood Project Value

Highland and its consultants have identified a number of opportunities to increase the value of the Copperwood Project. These include upgrading inferred mineral resources, increasing mine productivity utilizing innovative continuous mining technologies, conducting further geotechnical studies to optimize ore recovery and minimize mining dilution, reviewing tailings disposal alternatives, and conducting additional testing to maximize metallurgical recoveries.

Copperwood Project

The Copperwood Project property is located, by road, approximately 22.5 km to the north of Wakefield and 40 km from the town of Ironwood, both in Gogebic County, western Upper Peninsula, Michigan. The project area is at the south edge of the Keweenaw Copper province and underlain by clastic sediments of the Oronto Group, including the Copper Harbor, Nonesuch and Freda Formations.

The Copperwood and its “satellite” deposits are hosted by the limbs of the northwest dipping Presque Isle Syncline within the Nonesuch Formation. The Nonesuch Formation contains two mineralized sequences, one located at the base, the Lower Copper Bearing Sequence (“LCBS”) and a stratigraphically higher one, the Upper Copper Bearing Sequence (“UCBS”), separated by poorly mineralized sediments with a variable thickness of 0.5 m to 6.0 m.

Chalcocite is the only copper sulfide bearing mineral, occurring principally as disseminations within shale and siltstone. Individual disseminated grains of chalcocite are most commonly very fine grain, approximately 5 to 50 microns in diameter. The Copperwood deposit is relatively sub-horizontal with a thickness that varies from 1.6 m to 3.7 m.

Mineral Resources

GMSI prepared a Mineral Resource estimate for the Copperwood Project based on data provided up to and including April 12, 2018. The resource estimate was prepared in accordance with CIM Standards on Mineral Resources and Reserves (adopted May 10, 2014) and is reported in accordance with National Instrument 43‑101 (“NI 43‑101”) Standards of Disclosure for Mineral Projects. Classification, or assigning a level of confidence to Mineral Resources, has been undertaken with strict adherence to CIM Standards on Mineral Resources and Reserves. In the opinion of GMSI, the resource evaluation reported herein is a reasonable representation of the global Mineral Resources found at the Copperwood Project at the current level and spacing of sampling.

The mineral estimate was prepared under the supervision of Réjean Sirois, P. Eng. of GMSI, an independent “qualified person” as defined in NI 43‑101. Geovia GEMS™ and Leapfrog Geo™ software were used to facilitate the resource estimation process.

Total Measured and Indicated Mineral Resources of the Copperwood deposit are reported at 49.3 million tonnes grading an average of 1.54% Cu and 3.76 g/t Ag, containing 1.68 billion pounds of copper and 5.9 million ounces of silver using a cut-off grade of 1.0% Cu for the combined LCBS and UCBS. Inferred Mineral Resources are reported at 1.6 million tonnes grading an average of 1.18% Cu and 1.55 g/t Ag, containing 43 million pounds of copper and 0.1 million ounces of silver using a cut-off grade of 1.0% Cu.

Total Inferred Mineral Resources located in the satellite deposits are reported at 49.9 million tonnes grading 1.15% Cu and 3.42 g/t Ag, containing 1.27 billion pounds of copper and 5.5 million ounces of silver using a cut-off grade of 1.0% Cu for the combined LCBS and UCBS.

Mineral Resource Estimate

1.0% Cu Cut-off Grade – April 30th, 2018
DepositsResource
Category
Tonnage
(M t)
Copper
Grade
(%)
Silver
Grade
(g/t)
Copper
Contained
(M lbs)
Silver
Contained
(M oz)
LCBSMeasured27.31.684.581,0094.0
Indicated14.91.462.474791.2
M + I42.21.603.841,4885.2
Inferred1.61.181.55430.1
UCBSMeasured-----
Indicated7.11.213.261890.7
M + I7.11.213.261890.7
Inferred-----
Satellite LCBSInferred34.41.172.298882.5
Satellite UCBSInferred15.51.125.923843.0
Notes on Mineral Resources:
1) Mineral Resources are reported using a copper price of $3.00/lb and a silver price of $18/oz.
2) A payable rate of 96.5% for copper and 90% for silver was assumed.
3) The Copperwood Feasibility Study reported metallurgical testing with recovery of 86% for copper and 73.5% for silver.
4) Cut-off grade of 1.0% copper was used, based on an underground “room and pillar” mining scenario.
5) Operating costs are based on a processing plant located at the Copperwood site.
6) Assuming a $3.00/lb Cu price, a sliding scale 3.0% NSR royalty on the Copperwood Project is payable to leaseholders. Assuming closing of the acquisition of the White Pine Project, a 3% NSR royalty on the Copperwood Project payable to Osisko Gold Royalties Ltd. is reduced to a 1.5% NSR royalty.
7) Measured, Indicated and Inferred Mineral Resources have a drill hole spacing of 175 m, 250 m and 350 m, respectively.
8) No mining dilution and mining loss were considered for the Mineral Resources.
9) Rock bulk densities are based on rock types.
10) Classification of Mineral Resources conforms to CIM definitions.
11) The qualified person for the estimate is Réjean Sirois, P.Eng., Vice President Geology and Resources for GMSI. The estimate has an effective date of 30th April 2018.
12) Mineral Resources that are not mineral reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.
13) LCBS: Lower Copper Bearing Sequence.
14) UCBS: Upper Copper Bearing Sequence.
15) The quantity and grade of reported Inferred Resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as Indicated or Measured Mineral Resources.

Mineral Reserves

The Mineral Reserves estimate was prepared by Carl Michaud, P. Eng. of GMSI, in accordance with the CIM Standards on Mineral Resources and Mineral Reserves.  Mineral Reserves are based on Measured and Indicated Mineral Resources dated April 30, 2018 and do not include Inferred Mineral Resources. Measured and Indicated Mineral Resources are inclusive of Proven and Probable Reserves.

The Proven and Probable Reserves stated below were estimated based on these unconstrained Measured and Indicated Resources, noted above and the work carried out for the Feasibility Study.

Mineral Reserve Estimate

Reserve by CategoryTonnes
(M t)
Cu
Grade
(%)
Ag
Grade
(g/t)
Cu
contained
(M lbs)
Ag
contained
(M oz)
Proven17.51.504.43579.62.5
Probable7.91.282.50222.20.6
Proven & Probable25.41.433.83801.83.1
Notes:
1) The Mineral Reserves were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards for Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council May 10th, 2014.
2) Mineral Reserves are estimated at a cut-off grade of 1% Cu. The cut-off will vary depending on the economic context and the operating parameters.
3) Mineral Reserves are estimated using a long-term copper price of $3.00/lb and a silver price of $16.00/oz.
4) Assuming a $3.00/lb Cu price, a sliding scale 3.0% NSR royalty on the Copperwood Project is payable to leaseholders. Assuming closing of the acquisition of the White Pine Project, a 3% NSR royalty on the Copperwood Project payable to Osisko Gold Royalties Ltd. is reduced to a 1.5% NSR royalty.
5) Mineral Reserves are estimated using an ore loss of 3%, a dilution of 0.1 m for the floor and a 0.25 m for the back of the stope and the development.
6) The economic viability of the mineral reserve has been demonstrated.
7) A minimum mining height of 2.1 m was used.
8) The copper recovery was estimated at 86%.
9) The qualified person for the estimate is Carl Michaud, P. Eng., Underground Engineering Manager for GMSI. The estimate has an effective date of May 25, 2018
10) The number of metric tonnes was rounded to the nearest thousand. Any discrepancies in the totals are due to rounding effects; rounding followed the recommendations in NI 43‑101.

Mine Operations and Services

It is proposed to mine the deposit with a conventional highly mechanized, drill and blast room-and-pillar mining method. The method consists of the extraction of a series of entries and cross-cuts in the ore, leaving pillars in place to support the back. The entries, cross cuts and pillars have been sized using geotechnical analysis of the local host rocks, and experience from other mines sharing similar ground conditions.

The mine will be accessed via covered box-cut to establish a portal at the mine entrance from the surface, located at the central-west part of the deposit. The mine consists of two mining sectors: West and East. The western part, being higher grade with a thicker mineralized zone, will be mined in priority.

The mine is split into panels, which consist of at least 12 rooms that provide multiple headings where all activities of the mining cycle can be done in parallel to achieve high productivities, as opposed to activities in series as is the case in a single heading. The mining cycle consists of drilling, explosives loading and blasting, mucking, scaling and bolting.

Mining operations are planned with two 10-hour shifts per day, 360 days per year to achieve a production target of 2.4 M tonnes per year, or 6,600 tonnes per day. To achieve this production, a total of 7 to 9 panels must be in production at any given time.

The mining operation begins with drilling of the working face, which is accomplished with two-boom hydraulic-electric jumbo drills. Each round is drilled 4.25 m (14 ft) in length with an effective break of 4.00 m. The rooms are 6.1 m wide with a height that varies according to the ore column thickness. The height dimension dictates the productivity, which varies from panel to panel.

Mucking will be done with 10 tonnes load-haul-dump (“LHD”) units that will load muck at the mine face and transport it to the conveyor loading point established for the production panel. The LHD performance will be a function of dip of the stope and distance. The conveyor loading points will be regularly moved as production advances in the panel to be less than 250 m from the headings.

Scaling of the rooms is planned with a smaller low-profile LHD unit equipped with a scaling arm that rubs the roof to remove any loose rocks.

Bolting will be done by a mechanized bolter to install roof support and wall bolts. In the stopes, 1.8 m rebar bolts are required on a 1.2 m by 1.2 m pattern with wire mesh. In addition, 1.8 m friction bolts are planned in the pillars (i.e. walls) on a 1.5 m by 1.5 m pattern with wire mesh. At room intersection rebar bolt length is increased to 2.4 m.

Ventilation for the mine will be provided by a 400 m3/s fresh air raise and two exhaust raises at the eastern and western end of the mine. The dewatering system will consist of six pumping stations capable of evacuating 2,220 l/min of underground water inflow and mine water.

Highland continues to study the use of tailings as back-fill in the open stopes. If this approach is selected, it would provide cost savings for tailing disposal and closure costs.

Life-of-Mine (LOM) Metal Production

The LOM production for the Copperwood Project is shown below. Payable copper production is estimated at 300,000 tonnes (660 million pounds) with an annual average of 28,000 tonnes (61.7 million pounds) over the 10.7-year mine life which includes a 3-month commissioning and ramp-up period. The average payable rate is 95.8% which includes a 0.2% concentrate loss. Payable silver production over the LOM is 1.10 million ounces with an annual average of 101 thousand ounces of silver.

Production Physicals  Total
Concentratek of dmt1,264
Cu con. Grade% Cu24.7
Cu metal production M lbs690
Ag metal productionk oz2,296
Cu payable metalM lbs660
Ag payable metalk oz1,077

Processing and Metallurgy

The process plant design for the project is based on a metallurgical flowsheet designed to produce copper concentrate with a nominal throughput of 6,600 tpd and a planned availability of 91.3%.   The flowsheet consists of semi-autogenous grinding in closed circuit with a ball mill targeting a primary grind of 40 microns, rougher flotation with concentrate regrind, cleaner flotation using three stages of cleaning, concentrate thickening, filtration and tailings disposal.

The primary observation of variability testwork showed that the copper recovery varies from 77% up to ~ 90% with a concentrate grade from 20% up to 29% Cu. The overall average copper recovery is 86% with a weighted average copper concentrate grade of 24.7%. Studies show that copper recovery might be further increased by concentrate grade and reagents optimization.

Studies are underway to evaluate the optimal destination and transport option for the Copperwood concentrate.

Environment and Permitting

Environmental baseline studies were done for the Copperwood Project from late 2008 through the spring of 2011. These studies were used to identify existing and historical conditions in the Project area and select potential siting of infrastructures based on an environmental management and permit approvals perspective.

An Environmental Impact Assessment was prepared to comply with the State of Michigan requirements of Part 632 of Act No. 451 of the Public Acts of 1994 as amended. This document outlines the baseline monitoring and studies conducted for the Copperwood Project including the natural, social, economic, cultural, and historical aspects of the environment that may be potentially impacted by the Project design.

In order to construct and operate the Copperwood Project, a number of permits must be obtained and agreed upon between Highland and environmental regulatory agencies on both the state and federal levels. Highland maintains an open and proactive approach with both state and federal regulators.

The major environmental permits required to develop the Copperwood Project include: Part 632 Non-Ferrous Metallic Mining Permit; Part 31 National Pollutant Discharge Elimination System Permit; Part 55 Air Permit to Install; Part 301 Inland Lakes and Streams Permit; Part 303 Wetland Permit; Part 315 Dam Safety Permit; Part 325 Great Lakes Submerged Lands Permit; and Section 10 US Army Corps of Engineers Water Intake Permit.

Highland has filed amendment requests, renewals or new applications (as applicable) for these permits and expects to have all required permits by the fall of 2018.

Power and Surface Infrastructure

The Company is considering a 40 km 115 kV powerline supplied by a well-implemented energy provider in the state of Michigan. Detailed engineering will begin in the coming months for the best routing to minimize the impact on the environment. County Road 519 will be upgraded under the responsibility of the Michigan Department of Transportation.

Capital and Operating Costs

The initial capital costs, including all direct and indirect costs, are estimated at $275 million, including a contingency of $22.9 million. Pre-production revenue of $30.35 million reduces the capital expenditures to $244.6 million.

Initial Capital Expenditure Summary

Initial CAPEX  ($M)
General 1.150 
Infrastructure 36.650 
Power & Electrical 5.156 
Water & TDF Mgmt. 22.875 
Mobile Equipment 27.240 
Mine Infrastructure 53.529 
Process Plant 45.771 
Construction Indirects 27.609 
General Services & Owner's Costs22.251 
Pre-Production, Commissioning 9.838 
Sub-Total Before Contingency 252.069 
Contingency  9.1%22.899 
Total Incl. Contingency 274.968 
Less: Pre-Production Revenue (30.348)
Total Incl. Contingency & Pre-Prod. Revenue244.619 

Operating costs include mining, processing, G&A services, concentrate transportation and concentrate treatment and refining charges. The concentrate transportation, treatment charges and refining are deducted from gross revenues to calculate the net smelter return (“NSR”). The NSR for the Project during operations is estimated at $1.821 million, excluding $30.35 million of NSR generated during pre-production and presented as a reduction of initial capital expenditures. The average NSR over the LOM is $2.80 per pound of payable copper. The average operating cost over the LOM is $39.84 per tonne of ore or $1.53 per pound of payable copper with mining representing 53.4% of the total operating costs, or $21.26 per tonne of ore.

Sustaining Capital Expenditure Summary

The total LOM sustaining capital is estimated at $156.5 million.

Sustaining CapitalLOM
($M)
Tailings disposal facility expansion28.45
Water treatment plant6.13
Mine equipment purchases43.69
Mine development expenditures78.21
Total Sustaining Capital156.47

Operating Costs Summary

Operating Cash FlowLOM$/t ore$/lb Cu Payable
($M)
Cu Revenue2,04781.923.15
Ag Credits170.670.03
Revenue2,06482.593.17
Concentrate Transportation Costs943.750.14
Treatment & Refining Charges1495.960.23
Net Smelter Return1,82172.882.80
Royalties853.390.13
Mining Costs53121.260.82
Processing Costs30812.310.47
G&A Costs722.880.11
Total OPEX (incl. royalties)99639.841.53
Operating Cash Flow82633.031.27
Note: Ore tonnage and payable copper unit costs excluding commissioning period.

Sensitivity Analysis

 

  Variance

 
After-Tax Results
NPV 0%
($M)
NPV 8%
($M)
IRR
(%)
Payback
(yrs)
Metal Price Sensitivities
20%655.1318.831.9%2.1
10%486.1218.125.3%2.5
0%316.0116.818.0%3.2
-10%145.615.49.5%5.2
-20%-31.8-89.20.0%10.5
Initial Capital Cost Sensitivities
20%266.170.213.2%3.9
10%290.893.315.4%3.5
0%316.0116.818.0%3.2
-10%341.4140.421.1%2.8
-20%366.8164.024.7%2.5
Operating Cost Sensitivities
20%150.722.810.3%4.2
10%233.569.814.4%3.6
0%316.0116.818.0%3.2
-10%398.6163.921.3%2.9
-20%481.2210.924.3%2.6

Project Timeline

The timeline for the Copperwood Project is shown below. Subject to completion of financing and receipt of all necessary permits, construction could begin in January 2019. A 27-month construction period would see commissioning in the first quarter of 2021, with commercial production beginning in the second quarter of 2021.  

Project TimelineTotal
Construction (months)27
Mine development (months)20
Commercial production (yrs)10.7
Closure (months)27
Construction start dateJan. 1, 2019
Commercial prod. start dateApr. 1, 2021

Summary Economics for Copperwood Project

Summary Economics for Copperwood Project Total
Pre‐tax NPV @8% ($M)$  162.1 
Pre-tax IRR 21%
After‐tax NPV@ 8% ($M)$  116.8 
After-tax IRR 18%
Undiscounted After‐Tax Cashflow (LOM) ($M)$  316.0 
Payback Period from start of processing‐years 3.2 
  
Initial Capital expenditures ($M)$  275.0 
LOM Sustaining Capital Expenditures ($M)$  156.5 
LOM C‐1 Cash Costs $/lb (net of bi‐product)$    1.75 
Nominal Process capacity mt/d 6,600 
Mine Life‐years 10.7 
  
Annual Payable Metal Production 
Copper million pounds 61.7 
Silver thousand ounces 100 
  
LOM Average Process Recovery 
Copper % 86.0 
Silver % 73.4 

Feasibility Study Assumptions

Feasibility Study Assumptions Total
Avg. Copper Price ($/lb)3.15 
Avg. Silver Price ($/oz)16.00 
Treatment Charge ($/t)70 
Refining Charge (¢/lb)7.0 
Avg. Copper Payable Rate (%)95.8%
Avg. Silver Payable Rate (%)46.9%

All-in Cash Cost

 

LOM Costs
Total Cost
($M)
Unit Cost
($/tonne milled)
Unit Cost
($/payable lb)
Mining  531   21.26   0.82 
Processing  308   12.31   0.47 
G&A  72   2.88   0.11 
Offsite costs (transport, TC/RCs)  243   9.72   0.37 
By-product credits  (17)  (0.67)  (0.03)
C1 Cost  1,137    45.50    1.75  
Depreciation and closure  429   17.18   0.66 
Royalty costs  85   3.39   0.13 
C3 Cost  1,651    66.06    2.54  


 

First 5-Year Costs
Total Cost
($M)
Unit Cost
($/tonne milled)
Unit Cost
($/payable lb)
Mining  219   19.30   0.65 
Processing  140   12.34   0.42 
G&A  29   2.52   0.09 
Offsite costs (transport, TC/RCs)  130   11.45   0.39 
By-product credits  (13)  (1.18)  (0.04)
C1 Cost  504    44.43    1.50  
Depreciation and closure  159   14.00   0.47 
Royalty costs  45   3.95   0.13 
C3 Cost  707    62.38    2.11  

Qualified Persons

Louis-Pierre Gignac, P. Eng., of GMSI, an independent qualified person, as defined under NI 43-101, has read and approved the technical portions of this news release. The following qualified persons will be responsible for the preparation of their relevant portions of the technical report to be prepared in accordance with NI 43-101 and they have reviewed and approved this news release.

Qualified PersonsCompanyArea of expertise
Louis-Pierre Gignac, M.A.Sc., P. Eng.G Mining Services Inc.Operating cost estimation and economic analysis
Réjean Sirois, P. Eng.G Mining Services Inc.Geology and mineral resource estimation
Carl Michaud, P. Eng.G Mining Services Inc.Mineral reserve estimation and mine engineering
Paul Murphy, P. Eng.G Mining Services Inc.Infrastructure and capital cost estimation
Manochehr Oliazadeh, Ph.D, P. Eng.‎Lycopodium Minerals Canada LtdMineral processing and recovery methods
Ross D. Hammett, Ph.D, P. Eng.Golder AssociatesMine geotechnical engineering

Technical Report

The Company is planning to file a technical report in accordance with NI 43-101 on SEDAR, within 45 days from the date of this news release. Readers are cautioned that the conclusions, projections and estimates set out in this news release are subject to important qualifications, assumptions and exclusions, all of which are detailed in the Feasibility Study and technical report. To fully understand the summary information set out in this news release, the technical report that will be filed on SEDAR should be read in its entirety.

ABOUT HIGHLAND

Highland Copper Company Inc. is a Canadian company focused on exploring and developing copper projects in the Upper Peninsula of Michigan, U.S.A. The Company owns the Copperwood deposit through long-term mineral leases. The Company also owns surface rights securing access to the deposit and providing space for infrastructure as required. The Company has 472,933,689 common shares issued and outstanding. Its common shares are listed on the TSX Venture Exchange under the symbol "HI" and trade on the OTCQB Venture Market under symbol "HDRSF".

More information about the Company is available on the Company’s website at www.highlandcopper.com  and on SEDAR at www.sedar.com.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

This press release contains certain “forward-looking information within the meaning of applicable Canadian securities legislation. These forward-looking statements are made as of the date of this news release and Highland Copper Company Inc. does not intend, and does not assume any obligation, to update these forward-looking information, except as required under applicable securities legislation. Forward-looking information relate to future events or future performance and reflect Company management’s expectations or beliefs regarding future events and include, but are not limited to, information with respect to the estimation of mineral reserves and mineral resources, the conversion of mineral resources to mineral reserves, the expected timing for commencement of construction of the Copperwood mine, Highland’s ability to raise the necessary debt and equity contribution to the project, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, life of mine, environmental risks, the timing of the receipt of permits, the timing and terms of a power purchase agreement, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking information can be identified by the use of words such as “plans”, “expects” or “does not expect”, “is expected”, “outlook”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or information that certain actions, events or results “may”, “could”, “would”, “might” or “will be taken”, “occur” or “be achieved” or the negative of these terms or comparable terminology. In this document certain forward-looking information are identified by words including “scheduled”, “plan”, “planned”, “estimated”, “projections”, “projected” and “expected”. Forward-looking information are based on a number of assumptions which may prove incorrect, including, but not limited to, the development potential of the Copperwood Project and current and future metal prices and exchange rates. By their very nature forward-looking information involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include, among others, changes in project parameters as plans continue to be refined; future prices of commodities; possible variations in mineral reserves

CAUTIONARY NOTE TO UNITED STATES INVESTORS

Highland advises U.S. investors that this press release contains the terms "inferred", "indicated" and "measured" resources. All resource estimates have been prepared in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian standards differ significantly from the requirements of the United States Securities and Exchange Commission ("SEC"), and resource information contained therein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term "resource" does not equate to the term "reserves". "Inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred resource" will ever be upgraded to a higher category. U.S. investors are cautioned not to assume that all or part of an inferred resource exists, or is economically or legally mineable. U.S. Investors are also cautioned not to assume that all or any part of mineral deposits in the "measured" or "indicated" resource categories will ever be converted into reserves.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information, please contact:
Denis Miville-Deschênes, President & CEO
David Charles, Manager, Investor Relations
Tel: 1.450.677.2455
Email: info@highlandcopper.com  
Website: www.highlandcopper.com